Scope of work: Replacement, supply installation of 11 no's of air-cooled screw chillers having capacity 330tr each complete with associated new civil foundation, electrical panel, electrical power cable and mechanical work.
Challenge: To provide the highly efficient cost effective solution to client.
Solution: We have quoted the project with highly efficient York chillers with vsd, chiller pedestal with modification only, same incomer cable and switch gear panel.
Project status: All the chillers are installed and are working, balance grating installation and snagging work is in progress.